Centerton to Wilbur Transmission Line (Indiana)

It is our pledge that we will provide a free case review for any individual or business facing eminent domain or condemnation.

Project Overview

  • Location of Project: Indiana

  • Type of Project: Powerline

  • Timeline: 2023-2025

Project Details

The Hoosier Energy Wilbur to DEI Centerton 69kV reliability project involves building a 5.8-mile overhead transmission line. It will connect the Wilbur and Centerton substations in Morgan County, Indiana, improving grid reliability and reducing outages for SCI REMC members in Wilbur, Monrovia, and Mooresville while supporting future area growth.

Case Results

State: Wisconsin (Columbia County)

Case Type: Powerline takings

Initial Offer: $12,500

Sever Walker Padgitt Result:

$28,500

State: Illinois (Pike County)

Case Type: Powerline takings

Initial Offer: $185,093

Sever Walker Padgitt Result:

$215,916

State: Illinois (Pike County)

Case Type: Powerline takings

Initial Offer: $40,640

Sever Walker Padgitt Result:

$103,055

State: Illinois (Pike County)

Case Type: Powerline takings

Initial Offer: $55,000

Sever Walker Padgitt Result:

$159,798

State: Illinois (Morgan County)

Case Type: Powerline takings

Initial Offer: $119,517

Sever Walker Padgitt Result:

$159,000

State: Illinois (Christian County)

Case Type: Powerline takings

Initial Offer: $119,194

Sever Walker Padgitt Result:

$150,955

Meet Our Team

Sever Walker Padgitt Team Photo

At Sever Walker Padgitt, we pride ourselves on the expertise and dedication of our team. Get to know the faces behind the firm and discover the depth of knowledge and commitment that drives us to achieve the best possible outcomes for you.

Contact Us

Before going alone against the State let us give you our opinion. It is our pledge that we will provide a free case review for any individual or business facing eminent domain or condemnation. Contact us now at 888-318-3761

* Disclaimer: Form submission doesn’t constitute a client-attorney relationship/contract.