Project Overview
Project Details
Ameren Transmission Company of Illinois (ATXI), the Missouri Joint Municipal Electric Utility Commission (MJMEUC), and Ameren Missouri are partnering to enhance grid reliability through the Northern Missouri Grid Transformation Program—a two-phase effort delivering over 255 miles of new 345 kV transmission lines. Phase 1 includes the Fairport-Denny-Iowa/Missouri Border (FDIM) and Maywood-Mississippi River Crossing (MMRX) projects, adding about 53 miles of new line and a substation in Worth, Gentry, DeKalb, and Marion counties. Phase 2 features the Denny-Zachary-Thomas Hill-Maywood (DZTM) project, with over 200 miles of transmission lines and substation upgrades across ten northern Missouri counties.
Case Results
State: Wisconsin (Columbia County)
Case Type: Powerline takings
Initial Offer: $12,500
Sever Walker Padgitt Result:
$28,500
State: Illinois (Pike County)
Case Type: Powerline takings
Initial Offer: $185,093
Sever Walker Padgitt Result:
$215,916
State: Illinois (Pike County)
Case Type: Powerline takings
Initial Offer: $40,640
Sever Walker Padgitt Result:
$103,055
State: Illinois (Pike County)
Case Type: Powerline takings
Initial Offer: $55,000
Sever Walker Padgitt Result:
$159,798
State: Illinois (Morgan County)
Case Type: Powerline takings
Initial Offer: $119,517
Sever Walker Padgitt Result:
$159,000
State: Illinois (Christian County)
Case Type: Powerline takings
Initial Offer: $119,194
Sever Walker Padgitt Result:
$150,955
Contact Us
Let us give you our opinion before you go up against North Carolina alone. We pledge to provide a free case review for any individual or business facing eminent domain or condemnation. Contact us now at 888-318-3761.
* Disclaimer: Form submission doesn’t constitute a client-attorney relationship/contract.