Center Ridge Road Widening Project

This road project in North Ridgeville, OH plans to widen Center Ridge Road from three lanes to five lanes from Lear-Nagle Road to Stoney Ridge Road (2.3 Miles in length).  Costing roughly $55.4 million, the project will also include additional turning lanes, 6-foot wide sidewalks (north end), and 10-foot wide multi-use trail (south end).  The primary purpose of this project is to improve safety and congestion. 

The tentative time schedule for construction is as follows:

  • Completion of Right of Way Plans: November 2013
  • Completion of Roadway Plans: August 2014
  • Right of Way Acquisition: November 2013 – May 2015
  • Building Demolition: December 2014 – June 2015
  • Utility Relocation: June 2015 – November 2016
  • Construction: November 2016 – 2018

READ MORE: Center Ridge Road Widening Project

COMMERCIAL PROPERTY

What are the unique issues that face commercial property owners in condemnation that can make all the difference?

LEARN MORE

POWERLINES & PIPELINES

Landowners forget this one thing when dealing with utility companies that want an easement across their land.

LEARN MORE

ROAD & REDEVELOPMENT TAKINGS

What you need to know to be treated fairly by the condemning authority.

LEARN MORE